Incident Hub

A software patch was supplied from the vendor to correct an existing problem. This patch caused the SCADA server to fail, stopping the entire system. Operations of 3 plants were carried out on the one working PC, a standalone backup PC that had yet to be patched.

The system was restore to full operation by inserting a hard disk that was removed from the server prior to the patch being installed, this was the first time that the disk had been removed.

The software re-issued the patch with revised instructions detailing it was not to be used on the SCADA server.

No responses yet

    Deixe um comentário

    O seu endereço de e-mail não será publicado. Campos obrigatórios são marcados com *

    Latest posts

    Categories

    Latest Comments

    Nenhum comentário para mostrar.